Documentation - Project Scheduling

posted by -nEtPoSt- (Hasnul Azizi)

PROJECT SCHEDULING

  • Task Duration And Dependencies

Activity

Description

Duration(days)

Dependencies

T1

Define Project Scope

5

-

T2

Do Research

4

T1

T3

Do Survey

3

T1

T4

Prepare Proposal

2

T2

T5

Estimate Project

4

T2,T3

T6

Divide Tasks

1

T5

T7

Planning Process

3

T5

T8

Schedule Representation

3

T5

T9

Determine Risks

6

T6

T10

Determine Requirement

5

T3

T11

Calculate Costing

4

T6,T7,T8

T12

Manufacturer Purchases

5

T11

T13

Renovation Storage

7

T11

T14

Develop Hardware And Software

6

T11

T15

Monitoring And Review

3

T12,T13,T14

T16

Modeling System

7

T15

T17

Report

5

T16


  • Gannt Chart















































  • Pert Chart