- Manage Plan Information
| Work Plan Information | Example |
| Name of Task | Virtual Library System |
| Start date | 15th January 2010 |
| Completion date | 20th March 2010 |
| Resources needed | |
| Estimate time | 45 days |
| Actual time | 42 days |
- Workbreakdown
| Management Activities | Descriptions |
| 1) Prepare Proposal | Group give the specific name of our project. Our members discuss about the whole idea of project, and write the proposal |
| 2) Do Research | Discuss about the whole things in the project,the benefit of Virtual Library System, comparison with classic method and their vulnerabilities. |
| 3) Do Survey | Our group do an interview to the user and get the feedback. |
| 4) Submit Proposal | Send to our lecturer,Puan Yuhanim Hani |
| 5) Estimate Project | Determine the size,cost and time estimae in the beginning of our project. |
| 6) Divide Tasks | Each member is break into specific tasks based on their skills and list out all the task which divided. |
| 7) Planning Process | Determine duration time of the project,resource need. |
| 8) Graphical Schedule Representation | -Bar chart and activity network -skecth the Gant-Chart and Pert-Chart |
| 9) Determine Risks | Estimate types of risk,the risk that will be happen ,risk analysis and how to manage the risk |
| 10 )System Requirement | Identify functional and non-functional requirement and skecth use case diagram |
| 11) Calculate Costing | Determine the total budget and cost |
| 12) Manufacturer Purchases | Buy the manufacturer items |
| 13) Renovation Storage | Determine the capacity of storage needed to keep in the books in Library location. |
| 14) Develop Hardware And Software | List out the items needed to build and manage the system |
| 15) Monitoring And Review | |
| 16) Report | |